FIFA Funds US$13M Rebuild of Rizal Memorial Stadium in Manila

FIFA, PSC and PFF signed a deal on Nov 15 to rebuild Rizal Memorial Stadium with about US$13M. See the 20,000-seat plan, 15-month timeline and what it means.
November 18, 2026 by
FIFA Funds US$13M Rebuild of Rizal Memorial Stadium in Manila
Blocktec

By the Blocktec Editorial Team

FIFA, the Philippine Sports Commission (PSC) and the Philippine Football Federation (PFF) signed an agreement on November 15, 2026 to rebuild the Rizal Memorial Football Stadium in Malate, Manila. About US$13 million (around P828 million) of a US$25-million FIFA grant for Philippine football will go to the stadium. Construction is set to start in the first quarter of 2027 and aims to finish in 15 months.

The Agreement And Who Signed It

The memorandum of agreement covers the football stadium inside the Rizal Memorial Sports Complex. FIFA President Gianni Infantino, PFF President John Gutierrez and PSC Chairman Patrick Gregorio signed it. Executive Secretary Ralph Recto witnessed the signing, which took place during the ASEAN Football Federation Congress in Manila.

The roles are split clearly. The PFF leads planning, procurement and construction. The PSC provides the site, keeps ownership of it and continues to run the complex. The agreement runs for 30 years from turnover, meaning from the time the finished stadium is handed over.

The Money In Plain Terms

FIFA is giving about US$25 million for Philippine football as a whole. That package also covers academies and fields in the provinces, so not all of it goes to Manila.

Gregorio said about US$13 million of the grant, or around P828 million, is for the stadium, and that the PSC will not spend its own money on the project. Some figures put the stadium budget higher, at US$20 million, or about P1.275 billion. The gap between the two numbers has not been explained in the details released so far, so treat the final budget as unconfirmed until the PFF publishes its procurement figures. No contractor has been named yet.

What Will Be Built

Based on the mock-up presented by the PSC, the rebuilt stadium will seat about 20,000 spectators. The plan includes:

  • Higher stands
  • A roof over the seating
  • A natural grass pitch replacing the current artificial turf

The Art Deco facade will be kept and repainted. The design is by JR Partosa Arkiteks.

Heritage Status And Approvals

The complex was declared a National Historical Landmark in 2017. It hosted the 1954 Asian Games and the 1991 and 2005 SEA Games, and football has been played there for 92 years. Because of that status, the project must comply with the National Cultural Heritage Act.

Gregorio said the National Historical Commission has approved the master plan. The City of Manila, the Metropolitan Manila Development Authority (MMDA) and the Department of Public Works and Highways (DPWH) have also signed off.

Timeline And What Comes Next

Construction is set to begin in January 2027, with a target of about 15 months. That puts completion before the end of the Marcos administration. The next visible steps are the PFF's procurement process and the naming of a contractor, since the PFF is in charge of both. Builders watching this job should expect those announcements first, followed by mobilization at the Malate site.

What It Means For Builders

Fifteen months is a tight schedule for a roofed 20,000-seat stadium, especially one inside a heritage site where the facade stays and the work around it must be careful. The big structure, the roof and the pitch will take most of the attention. The interior is where schedule risk often hides: locker rooms, offices, medical rooms, storage and concourse partitions all have to be built, finished and inspected before opening.

This is where wall choice matters. Lighter walls put less load on the structure and are easier to move around a crowded site. A fire rating matters in a building where thousands of people will gather. Fast laying matters when several trades are waiting on each other. Blocktec's AAC blocks and panels have a 4-hour fire resistance rating and are laid with thin-bed adhesive and finished with skimcoat, so there is no thick plaster step (walang palitada). A trained mason with a helper does about 10-12 m2 per 8-hour shift, and up to 20 m2 on straight runs. In Blocktec's cost comparison, the wall system showed up to about 21% savings versus hollow blocks, depending on the project.

The same logic applies to your own projects, big or small. Check the schedule, the fire rating and the finishing steps before you fix the wall spec, not after. Blocktec supplies from hubs in Marikina, Subic and Cabuyao, Laguna.

Sources

Planning interior walls for a tight-schedule project like a stadium or sports facility? Send your wall area or blueprints to sales@blocktec.ph or blocktec.ph for a free AAC wall-system estimate.

in News
FIFA Funds US$13M Rebuild of Rizal Memorial Stadium in Manila
Blocktec November 18, 2026
Share this post
Our blogs
Archive