By the Blocktec Editorial Team
The last unfinished sections of the Cavite-Laguna Expressway (CALAX) and the 1.2-km CAVITEX-CALAX Link in Kawit are about 97% complete, and government officials are targeting an opening in the first week of December. Metro Pacific Tollways South (MPT South) says it has met the requirements and is waiting for final government approval. Once everything is open, travel from Kawit to the SLEX Mamplasan interchange would fall from more than two hours to about 45 minutes. This article is based on news published on November 19, 2026, with updates from the following days.
What Is Left To Open
Two CALAX subsections remain. Subsection 1 is 7.22 km long and runs from Centennial Road in Kawit to the Open Canal Interchange in Imus, Cavite. Subsection 2 is 10.53 km long and runs from Open Canal in Imus to the Governor's Drive Interchange in General Trias.
The third piece of work is the CAVITEX-CALAX Link, or CCLink. It is a 1.2-km, four-lane elevated viaduct in Kawit. It joins the southern end of CAVITEX to the northern end of CALAX, so drivers can move from one expressway to the other without going through local streets.
MPT South took Calabarzon media through these unfinished parts on November 21. Some figures put the unfinished length at about 18.5 km, so you may see slightly different totals depending on how the link and interchanges are counted.
Inspection, Approvals And The Opening Target
Transportation Secretary Vince Dizon and Public Works Secretary Giovanni Lopez inspected the sections on November 19. They put progress at about 97%. They said they would recommend to President Marcos that the roads open before Christmas, after a road safety audit.
The early-December target is ahead of the earlier projection of the first quarter of 2027. MPT South vice president Arlette Capistrano said the company has complied with requirements and is waiting for final government approval. No firm opening date has been set, and toll rates were not disclosed.
The Numbers: Travel Time And Reach
The full CALAX will run about 45 km from Kawit to the SLEX Mamplasan interchange in Biñan, Laguna. About 26 km is already open, up to Governor's Drive.
The DOTr estimates, in plain terms:
- Kawit to Mamplasan: from more than two hours to about 45 minutes.
- Governor's Drive to Kawit: from about 90 minutes to 15 minutes.
- Subsection 1 (Kawit to Imus): from 25 minutes to 8 minutes.
- Subsection 2 (Imus to General Trias): from 20 minutes to 11 minutes.
Officials said about 30,000 private motorists could benefit. For a delivery truck or a company shuttle, saving more than an hour each way on a single route changes how many trips fit into a working day.
Background: A 35-Year Concession Built In Stages
CALAX is a 35-year public-private partnership. The DPWH awarded it in 2015 to MPCALA Holdings, a unit of Metro Pacific Tollways. Sections opened in stages from 2019. Subsection 3, which reaches Governor's Drive, was inaugurated on May 4, 2026.
The Cavite portions took longer because of right-of-way problems, which is the usual hurdle when a road has to pass through land that is already occupied or owned by others.
What Happens Next: Exits And Local Roads
Secretary Lopez warned that traffic leaving the expressway could clog local roads. DPWH Region IV-A has started widening roads near the SLEX rotunda to ease the expected bottlenecks at the exit. The next milestones are the road safety audit, final government approval and a decision on the opening date. Toll rates are still to be announced.
What It Means For Builders In Cavite And Laguna
A faster link between Kawit, Imus, General Trias and Biñan changes how far materials, crews and finished goods can travel in a day. That tends to make sites along the corridor easier to supply and more attractive for warehouses, plants and subdivisions. We cannot say which projects will follow, since none were announced, but contractors and estimators in the area should plan for more demand and for tighter schedules.
Here is our practical view. If you are pricing walls for a project along this corridor, the wall system is one of the easiest places to save time. A trained mason with a helper lays about 10-12 m2 of AAC wall per 8-hour shift, and up to 20 m2 on straight runs. Blocks go up with thin-bed adhesive and a skimcoat finish, so there is no thick sand-cement plaster. Walang palitada means fewer trips for sand and cement and less cleanup on site. In Blocktec's own cost comparison, the wall system came out up to about 21% cheaper than hollow blocks, though results depend on the project.
Blocktec supplies from hubs in Marikina, Subic and Cabuyao, Laguna, so deliveries to Cavite and Laguna sites start from a nearby base. Before you finalize any spec, check the opening date and exit traffic plans, since both can affect your delivery schedule.
Sources
- Context.ph: Remaining CALAX segments, CAVITEX-CALAX Link target first-week December 2026 opening (Nov 19, 2026)
- Asian Journal: Major Luzon expressway nears opening, promising faster travel and trade (Nov 21, 2026)
- Daily Tribune: CALAX, CAVITEX link eyed for December opening (Nov 22, 2026)