Grand Central Station Build Restarts in QC; March 2028 Target

Construction of the P2.8-billion Unified Grand Central Station on North Avenue resumed on Nov. 11, 2026. See what DOTr said and what it means for builders.
November 19, 2026 by
Grand Central Station Build Restarts in QC; March 2028 Target
Blocktec

By the Blocktec Editorial Team

The Department of Transportation (DOTr) has restarted construction of the Unified Grand Central Station on North Avenue in Quezon City. Work formally resumed on Nov. 11, 2026, after Transportation Secretary Vince Dizon led a site inspection. The concourse covers about 13,700 square meters, the budget is P2.8 billion, and DOTr wants the station open to the public by March 2028.

What Is Being Built On North Avenue

The Unified Grand Central Station, also called the Common Station, is a rail interchange meant to tie together four lines: LRT-1, MRT-3, MRT-7 and the planned Metro Manila Subway. It is also designed to serve the EDSA Busway and other public utility vehicle terminals, so a commuter could change from rail to bus in one place.

Raised walkways are part of the plan. They are meant to let passengers transfer between lines without going down to street level or crossing EDSA. For anyone who has dodged traffic on that stretch, that is the main selling point.

The Numbers In Plain Terms

  • Concourse area: about 13,700 sq m. That is roughly the size of two full-size football fields.
  • Budget: P2.8 billion.
  • Resumption date: Nov. 11, 2026.
  • Target for public use: March 2028, which is about 16 months after work restarted.

DOTr has not released a revised cost, a progress percentage or a detailed construction schedule. Those figures are unknown for now, so any timeline beyond the March 2028 target should be treated as an estimate.

Why It Took So Long

The interchange has been delayed for close to two decades. Setbacks began in 2009. A long dispute over where the station should sit followed, and it was settled under former Transportation Secretary Arthur Tugade. Groundbreaking was held in September 2017.

DOTr later cancelled the contract of the original builder, BF Corp., and its partner Foresight Development and Surveying Co., citing excessive delays. A consortium led by Light Rail Manila Corp., the private operator of LRT-1, is now carrying the work forward.

Shifting Targets And What Comes Next

The completion goal has moved more than once. Earlier in 2026, DOTr spoke of a mid-2027 completion, and later of partial operations by the first quarter of 2028. Dizon now says the station should be ready for public use by March 2028, before President Ferdinand Marcos Jr. leaves office. The President has ordered the project accelerated.

DOTr said it will continue site monitoring toward that date. Watch for a published schedule, since that would show how the remaining work is sequenced.

What This Means For Builders

We have no information on the station's wall specifications or procurement, so what follows is our own reasoning, not a DOTr statement. Projects like this one, built against a fixed deadline and often near live rail operations, tend to reward materials that install quickly and cleanly. Station offices, utility rooms and partition walls are typical places where that matters.

That is where AAC (autoclaved aerated concrete) can fit. Blocktec's AAC carries a 4-hour fire resistance rating. A trained mason with a helper lays about 10-12 m2 per 8-hour shift, and up to 20 m2 on straight runs. Blocks go up with thin-bed adhesive and a skimcoat finish, so it is walang palitada, which means less wet work and less mess on site. In Blocktec's own cost comparison, the wall system came out up to about 21% cheaper than hollow blocks, though results depend on the project.

If you are bidding on or planning fit-out work for transit-adjacent buildings, or any job with a tight schedule, check your wall spec early. Blocktec supplies from hubs in Marikina, Subic and Cabuyao, Laguna, which helps with delivery planning across Metro Manila and nearby provinces. Ask for the fire rating, strength class and installation rate in writing, and compare them against your schedule.

Sources

Planning walls for a project with a tight deadline, like the work now restarting in Quezon City? Send your wall area or blueprints to sales@blocktec.ph or blocktec.ph for a free AAC wall-system estimate.

in News
Grand Central Station Build Restarts in QC; March 2028 Target
Blocktec November 19, 2026
Share this post
Our blogs
Archive