By the Blocktec Editorial Team
Maynilad Water Services said on October 27, 2026 that it has completed or is building close to P10 billion in upgrades at its La Mesa water facilities in Quezon City. The work is meant to keep supply steady as El Niño is expected to last into the first half of 2027. The upgrades let the plants treat much muddier raw water, add recovered water to the supply and turn old sludge lagoons into storage.
What Maynilad Is Building At La Mesa
Maynilad, the Pangilinan-led concessionaire for Metro Manila's West Zone, has spent or committed nearly P10 billion over several years to rehabilitate and upgrade its La Mesa facilities. The figure covers both finished and ongoing projects. The Philippine Star, Daily Tribune and BusinessWorld all reported the announcement.
Besides the headline turbidity work, the program includes sedimentation, filtration and sludge handling upgrades. It also covers monitoring systems and the replacement of old equipment. The company says the goal is to protect supply while PAGASA warns that El Niño will carry into early 2027.
Treating Muddier Water: The Turbidity Numbers
Turbidity measures how cloudy water is, in NTU. After heavy rain, raw water from the dam arrives full of silt, and the plant has to clean it before it can go to homes.
La Mesa Treatment Plant 1 has a design capacity of 1,500 million liters per day (MLD). It was originally built for raw water at about 300 NTU. It can now handle up to 2,000 NTU, more than six times the original design level. For comparison, the plant logged 818 NTU on August 30, 2026. The Angat-Ipo system has reached about 1,800 NTU before, in 2012, so the new limit covers a worst case that has actually happened.
La Mesa Treatment Plant 2, rated at 900 MLD, is getting similar upgrades. Together the two plants have 2,400 MLD of design capacity.
Recovered Water And Raw-Water Storage
Maynilad is also building three water recovery and raw-water augmentation systems. Once all are running, they will add 125 to 170 million liters per day. Systems 1 and 3 are already operating. System 2, which adds 50 to 70 MLD, is due in December 2026.
The company has also converted old sludge lagoons into reservoirs. Lagoons 3 and 4 now hold about 133 million liters of raw water. The target is 200 million liters by December 2026.
Why Angat Dam'S Level Matters
The urgency comes from the dam. Angat Dam fell to 150.42 meters in July 2026, below its July 2019 low of 157.96 meters. Maynilad says it has reduced its reliance on Angat by adding Laguna Lake plants, modular plants and deep wells. Angat now supplies 83% of Maynilad's treatment capacity, down from 100%.
Leak control is part of the picture too. Daily water losses fell by more than 150 million liters between June 2025 and June 2026. Maynilad serves 17 cities and towns in Metro Manila's West Zone under its MWSS concession.
What Officials Said And What Comes Next
Chief Operating Officer Christopher Lichauco said supply security depends on how well water is treated and recovered, not only on how much raw water arrives. Water supply head Ronaldo Padua addressed the bucket filtration idea floated by DSWD Secretary Rex Gatchalian. He said it suits areas with no surface water, and that Maynilad aims to make it unnecessary in its service area.
Maynilad has not imposed rotating water interruptions. It does say the upgrades reduce the risk of a long shortage but do not remove it. The next checkpoint is December 2026, when system 2 and the 200-million-liter storage target are due.
What This Means For Builders
A capital program of this size usually means steady work for contractors on plant buildings, pump houses, control rooms and other support structures. If you build or supply for utility projects, it is worth asking Maynilad's contractors what is coming up for bid. We have no information on specific tenders, so treat this as a lead to check, not a confirmed opportunity.
Buildings like these tend to need fire-rated, low-maintenance walls. Blocktec's AAC blocks carry a 4-hour fire resistance rating. They are laid with thin-bed adhesive and finished with skimcoat, so it is walang palitada, with no thick sand-cement plaster to wait on. A trained mason with a helper does about 10-12 m2 per 8-hour shift, and up to 20 m2 on straight runs. In Blocktec's own cost comparison, the wall system came out up to about 21% cheaper than hollow blocks, depending on the project.
The broader lesson from La Mesa is planning for stress before it arrives. For any build, set your wall spec, schedule and budget early, before a squeeze on time or materials forces rushed choices.
Sources
- Philippine Star: Maynilad pours in P10 billion for La Mesa upgrades (Oct 28, 2026)
- Daily Tribune: Maynilad pours P10B into water supply upgrades (Oct 27, 2026)
- BusinessWorld: Maynilad sets P10B for La Mesa upgrades amid El Niño threat (Oct 27, 2026)